Pre-engineered steel frames are shop-fabricated, trucked to site and bolted together. Below is data from an actual 13-piece rigid frame building.

Basic Specs
| Item | Value |
|---|---|
| Frame ID | GJ-1 |
| Total pieces | 13 (7 columns + 6 beams) |
| Total weight | 7,920.7 kg (7.9 t) |
| Material | Q355B |
| Column type | Tapered WH(300~700)×300×8×12 |
| Beam type | Tapered WH(700~400)×300×8×12 |
| Column height | 11.5–12.3 m |
| Connection | M20 high-strength bolts, shop-plated |

Component List
| Member | Section | Length | Weight |
|---|---|---|---|
| GZ-1 column | WH(300~700)×300×8×12 | 11,517 mm | 1,081 kg |
| GZ-2 column | WH300×300×8×14 | 11,895 mm | 998 kg |
| GZ-3 column | WH300×300×8×14 | 12,315 mm | 1,011 kg |
| GZ-4 column | WH300×300×8×14 | 11,925 mm | 998 kg |
| GZ-5 column | WH(300~700)×300×8×12 | 11,522 mm | 1,079 kg |
| GL-1 beam | WH(700~400)×300×8×12 | 3,729 mm | 344 kg |
| GL-2 beam | WH400×250×8×10 | 8,159 mm | 573 kg |
| GL-3 beam | WH(400~700)×300×8×12 | 3,779 mm | 348 kg |
| GL-4 beam | WH400×250×8×10 | 8,460 mm | 595 kg |
| GL-5 beam | WH(400~600)×250×8×12 | 4,080 mm | 376 kg |
| GL-6 beam | WH(600~400)×300×8×12 | 4,228 mm | 382 kg |
The speed comes from three design choices:
Shop-fabricated pieces: every member cut, welded and drilled in factory
Bolted connections: M20 bolts, no site welding needed
Tapered sections: tapered columns and beams use only where load is high
Pre-drilled holes: -80×10 cover plates with holes match M20 bolts
Lift-and-bolt: column lifted, beam set, bolts tightened — done
Days not weeks — 13 pieces erected in 2–3 days with one crane
No site welding — bolted connections clean and fast
Q355B lighter — Q355B sections weigh less than Q235 same load
Tapered saves steel — tapered column uses 300mm at base, 700mm at top
Weather independent — bolted erection works in rain and cold
Factory lead time — needs 4–6 weeks fabrication before delivery
Crane needed — 1-ton pieces need lifting equipment
Bolt inspection — every M20 bolt must be torqued and checked
Transport limits — 12m columns need long trucks
Foundation prep critical — bolt group positions must match exactly

Typical Applications
Rapid-build factories — production starts in weeks
Warehouse expansion — add space fast
Temporary buildings — event halls, emergency shelters
Remote sites — no welding needed on site
Cold-weather construction — bolted works in winter
Columns lifted and bolted to base plates
Beams lifted and bolted to column brackets
Cover plates -80×10 installed at splices
All M20 bolts torqued to spec
Bracing and purlins follow
Pre-engineered steel rigid frame — 13 pieces, 7.9 tons total, Q355B tapered columns and beams, M20 bolted connections, shop-fabricated and trucked to site, erected in days for factory and warehouse buildings.
**WhatsApp**: +86‑13889862778, +86‑18242444407
**Email**: eddie@zdsteels.com, wells@zdsteels.com
YOU MAY LIKE