Shear studs (headed studs) weld to the top flange of steel beams, locking the concrete slab to the steel beam so they work as one composite unit. Below is data from an actual composite beam project.

Basic Specs
| Item | Value |
|---|---|
| Product | Shear stud / headed stud |
| Standard | G/T 10433 |
| Material | ML15 |
| Size | φ22 × 150 mm |
| Unit weight | 0.5 kg/pc |
| Quantity | 6,816 pcs |
| Total weight | 3,408 kg (3.4 t) |
| Application | Steel-concrete composite beam |

Shear studs connect steel beam and concrete slab:
Welded to beam: stud welded to top flange of steel beam
Embedded in slab: concrete poured around studs
Shear transfer: studs resist horizontal slip between steel and concrete
Composite action: steel beam + concrete slab act as one T-beam
Composite efficiency — studs make steel and concrete work together, saving 20–30% steel
Fast welding — stud welding gun fires in seconds, no manual lay-up
High shear capacity — φ22 stud carries ~100 kN shear per stud
Automatic welding — drawn arc stud welding, consistent quality
Standard system — Q355 beam + C30 slab, widely proven
Welding equipment needed — requires stud welding machine, not ordinary welder
Weld inspection — each stud bend-tested after welding
Concrete must cover — slab must be thick enough to embed studs
Corrosion at base — stud base weld can rust if slab leaks
Layout optimized by analysis — too few studs = slip, too many = waste

Composite floor beams — steel beam + concrete slab in office buildings
Bridge decks — steel box girder + concrete deck composite
Composite columns — concrete-filled tube with shear connectors
Mezzanine floors — existing building added floor, composite beams
Parking garage decks — long-span parking structure floors
Studs drawn-arc welded to top flange of steel beam in shop
Welding voltage and time set per φ22 stud spec
After welding, bend 30° test on sample studs
Concrete slab poured after deck mesh placed around studs
Shear studs — ML15, φ22×150 mm, 6,816 pcs, 3.4 tons total, drawn-arc welded to steel beam flanges, locking concrete slabs for composite beam action
**WhatsApp**: +86‑13889862778, +86‑18242444407
**Email**: eddie@zdsteels.com, wells@zdsteels.com
YOU MAY LIKE