Drawing note: member sizes, lengths, grades and weights are read from the material table; plan and section dimensions from the 1:25 structural plan and 1:50 section. Gutter plate thickness, roof slope details, connection weld size and foundation load are not listed in this batch.
TL-1 is the steel support beam carrying the eaves gutter at axis A2. The main member is two back-to-back C18a channels, 4,491 mm long, Q235B; four short C18a pieces 322 mm long act as connectors and stiffeners. One finished beam weighs 210.2 kg, with eight M20×50 HS bolts connecting to the frame. The section shows the beam standing on the 3,150 mm pile cap at +0.220, beam height 2,626 mm under a 0.6 mm profiled metal roof with 5% fall.
![]()
Material Table — TL-1
| Part | Section | Length (mm) | Grade | Qty | Unit weight (kg) | Total (kg) |
|---|---|---|---|---|---|---|
| C-1 | C18a channel | 4,491 | Q235B | 1 | 90.6 | 90.6 |
| C-1 | C18a channel | 4,491 | Q235B | 1 | 90.6 | 90.6 |
| C-2 | C18a channel | 322 | Q235B | 4 | 6.5 | 26.0 |
| Weld (1.5%) | — | — | — | — | 3.1 | 3.1 |
| Bolt | M20×50 | — | HS | 8 | — | — |
| TL-1 total | — | — | — | 1 beam | 210.2 | 210.2 |
Weight check: 90.6 + 90.6 + 26.0 + 3.1 = 210.3 kg, matching the 210.2 kg beam total.
表格
| Item | Value |
|---|---|
| Plan bay | 4,000 mm wide (2,000 + 2,000); 5,000 mm deep, 500 mm edge each |
| Beam position | Axis A2, centered between axes 33 and 44 |
| Section beam height | 2,626 mm; adjacent column height 3,000 mm |
| Top bearing width | 3,040 mm |
| Pile cap | 3,150 mm wide; 1,150 + 2,000 + 1,850; cap thickness 80 mm |
| Cap elevation | +0.220; column edge 150 mm |
| Roof build-up | 0.6 mm profiled steel sheet, purlins, frame |
| Roof fall | 5% each way |
| Cleat detail (node 1) | 3 mm plate, 390 mm wide, 80 mm high |
| Plan bracing | SC-1 cross ties; XG-1 edge tie rods; GJ-1 frame beams |
Double channel carries the gutter. Two C18a channels back-to-back form a short-span beam that carries the gutter and its dead weight plus rain load.
Short channels tie the members together. Four 322 mm C18a pieces act as end connectors and intermediate stiffeners between the main channels.
Bolts fix the beam to the frame. Eight M20×50 HS bolts connect TL-1 to the adjacent GJ-1 frame members and supports.
Beam transfers load to the cap. The 2,626 mm high support stands on the pile cap, passing reaction through the base to the foundation.
Roof drains toward the gutter. The 5% two-way fall sends roof water to the eaves gutter supported on TL-1.
Prefabricated channel member — shop-assembled as one 210.2 kg beam, bolted on site; no field channel splicing.
Standard C18a section — channel is a routine stocked shape; replacement and detailing are straightforward.
Lightweight and narrow — a short eaves support that does not compete with the main frame for headroom.
Bolted connections — eight M20×50 bolts allow removal and replacement without cutting steel.
Clear bracing layout — SC-1 cross ties and XG-1 rods stabilize the frame panel around the support.

Disadvantages / Limits
Channel open-face corrosion — exposed channel slots collect dirt and water; painting and drainage gaps need attention.
Gutter load not specified here — rainwater depth, debris surcharge and gutter panel weight are not listed; channel size must be checked against actual drainage load.
Short stiffener spacing — the four 322 mm connectors control channel buckling; missing or weak stiffeners reduce capacity.
Base connection detail incomplete — base plate, anchor bolts and weld size are not in this batch; base fixity needs the detail drawing.
Data gaps — steel proof stress, bolt grade/torque, beam span between supports and foundation reaction are not given; capacity needs the original design.
Industrial steel workshop eaves supporting an edge gutter along the roof perimeter.
Warehouse and logistics building gutter brackets at low-slope metal roofs.
Steel frame side drainage beams where a channel bracket carries gutter cladding and downpipe supports.
Portal frame edge members tied to GJ-1 frame beams and SC-1 bracing.
Retrofit eaves additions where a bolted channel support is added to an existing frame.

Fabrication and Erection Notes
Verify Q235B channel material and the HS bolt specification; confirm bolt grade and torque from the original design.
Match the material table: two 4,491 mm C18a channels, four 322 mm C18a pieces, weld allowance 1.5%.
Set out TL-1 on axis A2; check the 2,626 mm height, 3,040 mm top width and alignment to the gutter.
Fix SC-1 cross ties and XG-1 rods before loading the beam; check panel alignment.
Install the eight M20×50 bolts; do not omit bolts at the frame connection.
Paint channel interiors and contact surfaces; keep gutter drainage paths clear of dirt and sealant.
A Q235B gutter support beam TL-1: two C18a channels 4,491 mm long, four 322 mm short channels, 3.1 kg weld allowance, one beam 210.2 kg, eight M20×50 HS bolts, 2,626 mm high in a 4.0×5.0 m bay under a 0.6 mm metal roof with 5% fall. Sections, lengths and weights come from the material table; gutter load, bolt grade and base detail follow the original design.
**WhatsApp**: +86‑13889862778, +86‑18242444407
**Email**: eddie@zdsteels.com, wells@zdsteels.com
YOU MAY LIKE